Wynne Walker Group · Lighting & Technology Consulting
Builder action items

Smith Residence

11 Stillforest · Updated Oct 21, 2026
7
Open items waiting on the builder
4
Electrical
2
Tech / low voltage
1
Lighting control
⬇ Download full builder report (PDF)Fieldwire builder report · generated Oct 22, 2026 · 22 pages, 4.8 MB

Open items by trade

Open items by month opened

Items waiting on the builder

#ItemTradePlan sheetOpened
#244Move WAP wiresTechX-1.02Jan 2, 2026
#282Doorbell will go here – keep an eye on this once they start the stoneTechX-1.01Jan 6, 2026
#437Ask John if there is still a medicine cabinet hereElectricalE-1.02Apr 15, 2026
#489Center keypadLighting ControlLT-1.01Aug 5, 2026
#491Outlet not centered (we did not show it centered!)ElectricalE-1.01Aug 5, 2026
#512They are moving these to be in the side of the millworkElectricalE-1.02Aug 6, 2026
#514Try to put in millwork panel?ElectricalE-1.02Aug 6, 2026
Numbers match the task numbers in the Fieldwire project "Smith - 11 Stillforest". Find each item on the plan sheet listed.